Service
Design, permits and grid connection of solar plants
Technical conditions, detailed design, approval by the grid operator, testing and metering. As a separate service for sites installed by another contractor, or as part of a turnkey project.
- Power
- from 10 kW to 3+ MW
- Who it is for
- clients with their own installation crew, installers without a design department, site owners who need a grid connection
What is included
- Feasibility study and choice of the connection scheme
- Application for and obtaining of technical conditions from the distribution system operator
- Detailed design of the electrical part, mounting and earthing
- Approval of the design, with an expert review where needed
- Testing, test reports, metering point
- Commissioning, active consumer or generating facility status
Stages and timelines
Timelines are approximate; the exact ones are fixed in the contract.
- 1 2–3 days
Initial data
Supply contract, connection capacity, site plan, a year of metering data.
- 2 per the operator's regulations
Technical conditions
Application to the distribution system operator, obtaining and reviewing the technical conditions.
- 3 2–4 weeks
Design
Detailed design, specifications, diagrams, agreement with the client.
- 4 2–4 weeks
Approval
Approval of the design by the grid operator, expert review for the sites that require it.
- 5 2–4 weeks
Connection
Testing after installation, test reports, metering, contract and commissioning.
- The time limits for issuing technical conditions and for approval are set by the distribution system operator's regulations and the Distribution System Code.
- Plants that sell energy need a licence or membership in an association under the current market rules.
When it is ordered separately
When you have your own installers, or the equipment is already bought and only the paperwork is needed: technical conditions, design, approval, connection. Installers without a design department hand the electrical part over to us. We take sites from 10 kW up to multi-megawatt ground-mounted plants and see them through to energisation.
Technical conditions
An application to the distribution system operator with the capacity, connection point and operating mode. The operator issues the technical conditions: the connection point, the requirements for protection and metering, and for large plants, measures in the grid. We prepare the application and documents, represent the client under a power of attorney and check that the requirements are realistic.
Detailed design
Single-line diagram, string and cable calculations, protection, earthing, metering point, scheme of interaction with the grid. For roofs, the load on the roofing and a layout that accounts for shading; for ground-mounted plants, the placement of the tables, cable routes and the substation. The specification lists specific models from stock: 650 W panels, inverters, PV Combiner Box DC cabinets, cable and mounting, as at the 2.4 MW plant in Ovruch.
Approval and expert review
The operator checks the design against the technical conditions; sites of a certain consequence class need an expert review, which we organise. Approval usually takes two to four weeks, the expert review about the same.
Testing and metering
Insulation resistance, phase-to-neutral loop, earthing, protection, inverter operation on the grid. The laboratory test reports go to the operator together with the acceptance certificate. The metering point follows the technical conditions: a bidirectional meter, and for large plants an automated commercial metering system (ASKOE).
Operating mode
A plant for self-consumption gets active consumer status and sells its surplus under net billing. A plant built to sell energy signs a contract on the market; large sites need a generation licence, which Sonnen Energy holds for its own plants.
What affects the timeline
Waiting for the technical conditions and the approval takes the longest, so we file the application in the first week. If the nearest substation lacks capacity, the technical conditions require measures in the grid that extend the project by months. Without a supply contract, a switchboard diagram or land documents, the process stops at the application stage. The timelines are indicative for sites of 30–500 kW.
What we need from you
Your electricity supply contract, the connection capacity, documents for the site or land, an up-to-date switchboard diagram and a power of attorney to deal with the operator.
Case study
A 2.4 MW ground-mounted solar plant in Ovruch, Zhytomyr Oblast: piles, tables, bifacial modules, Bluesun inverters and DC cabinets, cable routes. Built for a client.
- Power
- 2.4 MW
- Type
- Ground-mounted solar plant
- Installation
- Our own crew
Frequently asked questions
Who handles the grid connection?
We do. We prepare the application for technical conditions, develop the design, get it approved by the distribution system operator, arrange the metering and testing, and see the plant through commissioning. The client signs the documents and receives a finished plant.
For plants that sell their surplus, we arrange active consumer or generating facility status, depending on the capacity and the purpose.
What is net billing, and can I sell my surplus?
Net billing is a self-generation mechanism for active consumers: the electricity that the plant exports to the grid is credited at the market price and offsets the cost of the electricity consumed. It works for private homes and businesses whose generation is within the permitted capacity.
The terms depend on the contract with the supplier and the current version of the law.
What if my grid connection capacity is not enough?
First we check whether the connection really needs to be increased: storage often takes off the peak load, and no increase is needed. If it is needed, we prepare the application for a capacity increase, the technical conditions and the design; this is part of the grid connection service.
Get a quote
Describe the site and its connection capacity.
- 1 We reply within one working day
- 2 We clarify the site, consumption and the connection capacity
- 3 We send a quote with equipment and lead times within 1–4 days


